NYC-WTC_000162976–000162977Folder label: “E-mails 2003 M. Gilsenan”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
'p f Gilsenan, Michael From: Dave Stanke[ PII Sent: Tuesday, February 25,.20037:02 PM To: Michael Gilsenan Cc: Steven Elghanian; Steven Abramson; Karen Greenspan; David E. Stanke; Daniel Kaner; Mark Wainger Subject: Can we delay the start of our project?
Importance: High
Mike, I believe that we need to allow one extra week before the start of our reclamation project for 114 Liberty. We have been working hard to ensure that all of the pieces are in place for the work to begin, but a couple of areas are still uncertain. In addition, I'd like everyone to meet with you on Wednesday (tomorrow) and then to have time to go through their apartments before doing a final walk through with you and your contractors. The bad weather of a couple of weeks ago delayed our efforts, and also delayed this critical meeting.
The primary areas at risk are: Removal of all cabinetry from the walls in apartments choosing to do so. This should be completed by Wednesday of next week. A few windows need adjustments. They have not arrived at the building yet, and might not be completed until next week. We are having trouble getting Con Ed to switch the electricity on the building over to the condo meter. This is necessary for us to get electricity on every floor.
We prefer to set a hard date which we know we can all make rather than press for a date that we may not make. We would also like to know who the contractor is and review their estimates prior to having them work in our building. I have no doubt that you have executed this project in the quickest and most complete way. We will still be more comfortable after we review everything, since these are our homes which we are turning over to your contractors.
Can we please plan to start the cleaning on Friday, March 7th. This will also allow us to gather all of the signed documents and work through any issues individuals might have with the project.
Thank you for your consideration of this request.
Regards, Dave Stanke
-----Original Message-.-_-.--........................................ From: Denise Sweeny I PII Sent__ M_o_ndav, February 24 }2003 2:16 PM To • ._._._._. _ P11 Subject: coned
the phone numbers for con ed are: 212.243.1900 and 800.752.6633. our main account number is 43-2101-0398-0005-1.
i've made first contact, and awaiting intructions on how to proceed. I've no record of individual account numbers.
let me know if you have any better luck from your end - i'll keep trying from mine.
1
NYC-WTC 000162976
OCR can misread numbers and units. Confirm readings against the page image before using them.
Related records
Browse subjects →Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
Same-box records
1 shared topics · Same agency, volume and box · similarity 0.920
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000163858
DEP notification of air monitoring audit schedule changes with assigned personnel for WTC-related environmental monitoring activities.
1 shared topics · Same agency, volume and box · similarity 0.920
machine-extracted · confidence unavailable · Check page ↗1 shared topics · Same agency, volume and box · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000164438
Memo forwarding purchase order requisition number for medical monitoring services, pending second bid due to funding delays.
1 shared topics · Same agency, volume and box · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗Filed elsewhere
1 shared topics · similarity 0.996
machine-extracted · confidence unavailable · Check page ↗1 shared topics · similarity 0.926
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000162662
Submission of a preliminary scope of work document detailing procedures to safely clean the 114 Liberty Street building.
1 shared topics · similarity 0.925
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000163521
Directive to reduce sample collection flow rate to control analytical costs in WTC sampling.
1 shared topics · similarity 0.920
machine-extracted · confidence unavailable · Check page ↗1 shared topics · similarity 0.919
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000164290
Internal discussion regarding Declaration of Emergency, air monitoring requirements, FEMA grant coverage, and contract structure for debris cleanup operations.
Similar document embedding; no shared entity or topic indexed. · similarity 0.918
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000163640
Daily summary of calls received at the WTC hotline covering cleaning, environmental conditions, and health referrals.
Similar document embedding; no shared entity or topic indexed. · similarity 0.917
machine-extracted · confidence unavailable · Check page ↗More like this page
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000138498
Meeting scheduling for 114 Liberty cleanup project to determine scope, specifications, and execution details, with window work completion in early February.
Similarity score 0.960 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000138499
Emails coordinating alternative dates for a meeting to determine the scope of work at 114 Liberty.
Similarity score 0.955 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Similarity score 0.954 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155525
Initial draft of the comprehensive scope of work required to safely clean 114 Liberty Street following environmental damage.
Similarity score 0.954 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000138520
Confirmation of January 16, 2003 meeting at 114 Liberty to finalize cleanup project scope, specifications, and execution timeline.
Similarity score 0.951 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Others also read
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Filed in the same folder
NYC-WTC_000162755
Contractor submits apartment log and cost data requested for WTC cleanup project.
Filed in the same folder
NYC-WTC_000162771
Contractor submits a requested list of items for the WET environmental cleanup project.
Filed in the same folder
NYC-WTC_000162791
Asbestos removal contractor reports summary of apartments and common spaces cleaned in WTC Quad A sector.
Filed in the same folder
Filed in the same folder