December 17,2002 114 LIBERTY STREET
REMOVAL OF DUST, DEBRIS, AND CONTAMINATED MATERIALS
5. Gross cleaning of the entire area;
6. Removal and proper disposal of all exposed hardwood flooring, followed by
gross cleaning of the sub-flooring using HEPA vacuuming and wet wiping
techniques;
7. Removal, bagging and disposal, as asbestos contaminated waste, of any
in-place carpeting;
8. Fine cleaning of all remaining surfaces.
d. Complete decontamination of the Work Areas (refer to Section 13 for details).
5, Proper clean up. transport, and disposal ofwaste. Waste stream shall be segregated
into three categories. All porous items, dust and debris as well as rags and cleaning
materials, clothing etc. shall be disposed of as asbestos contaminated waste. All non-
porous items (i.e. unlined HVAC ducts, BX electrical cables, hardwood flooring, etc.),
following a gross cleaning by the General Contractor, shall be disposed of as
construction and demolition waste.
6. If required, Contractor to provide fire/security watch 24-hours, 7-days a week.
7. Contractor shall have a NYS and NYC licensed asbestos abatement supervisor on site
at all times while work is being performed. No work will be allowed whenever there is no
supervisor on site.
B. Sequence of the work shall be as follows:
1. Contractor to provide all required signage on ail floors (see Sections 07 and 11 of this
document). Post permits in locations as required.
2. Contractor to construct centrally located personal and waste decontamination chambers.
3. Contractor to install temporary lighting and power. All electricians to have Restricted
Handlers license.
4. Contractor to install isolation barriers over windows, doors, ceiling penetrations, etc.
using two layers of 6-mil polyethylene sheeting and sealed with tape, and protect the
floor with two layers of 6-mil reinforced polyethylene sheeting and sealed with tape;
5. Contractor to position Air Filtration Devices (AFDs) to obtain negative pressure in the
Work Area. Final location to be approved by Ambient Group, Inc.
6. Where required. Contractor to provide wooden isolation/bamers at staircases, elevators,
lobbies, corridors and all areas where opening is greater than 32 square feet to restrict
entry to the Work Area and facilitate total isolation. All materials shall be fire retardant.
7. Contractor to construct wooden manifolds at windows to both accept the exhaust from
the AFDs and to provide for make-up air via HEPA-filtered, manually controlled dampers.
The exterior of the manifolds shall be painted black.
8
© AMBIENT GROUP, INC. - 2002 SUMMARY OF WORK
NYC-WTC_000155725