December 17,2002 114 LIBERTY STREET
REMOVAL OF DUST, DEBRIS, AND CONTAMINATED MATERIALS
8. Contractor to ensure and demonstrate that Work Area is under a minimum of 0.02” wc
negative pressure via AFDs through use of recording manometers.
9. Contractor to completely remove dust contaminated materials from piping, fittings,
ceilings, “I” beams, walls, doors, floors, etc. as shown and/or noted in these documents,
and dispose of the materials as designated by these specifications.
10. Contractor to remoie any other materials as noted in Contract Documents.
11. Contractor to completely clean the entire Work Area using standard wet-wiping and
HEPA-vacuuming decontamination procedures.
12. Ambient Group, Inc. to certify work area(s) clean using the clearance criteria described
in Section 05 - Air and Wipe Sampling, and Section 14 - Work Area Clearance.
13. Contractor shall then remove all isolation barriers and seals, reinstall altered building
components and again clean the Work Area.
14. Contractor is responsible for all costs associated with failure of the clearance testing
criteria (i.e., re-cleaning and re-testing) as described in Section 05 - Air and Wipe
Sampling, and in Section 14-Work Area Clearance.
END OF SECTION 01
9
© AMBIENT GROUP, INC. - 2002 SUMMARY OF WORK
NYC-WTC_000155726