NYC-WTC_000128550
Asbestos inspection report notification form submitted to NYC DEP for 102-104 Greenwich Street.
13 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗Application form submitted to the Department of Environmental Protection for notification of an asbestos inspection project.
NYC-WTC_000154680–000154700Folder label: “Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
10. Clean and remove all non-porous materials from the work area and dispose as construction and demolition debris. 11. Remove all other porous materials (including existing non-asbestos containing fireproofing from steel beams, columns metal deck and all other surfaces, as well as pipe insulation and gypsum wallboard) from the work area and dispose of as asbestos contaminated waste. 12. Perform fine cleaning of the entire work area. 13. Environmental Consultant performs visual clearance testing of the floor work areas. As each floor passes visual clearance, contractor will seal of the floor until all work is completed so as to prevent re-contamination. Final air sampling will be performed for all floors upon completion of work. 14. Clean Securtity Elevator #24 in its entirety, including the shaft, via wet-wipe and HEPA vacuum methods. 15. Environmental Consultant performs clearance of the Car #24 shaft.
It is the performance objective of this project that the only materials to remain in the work area after clearance sampling is complete will be sprinkler piping, class “E” wiring and closed conduit.
2.2 FULL CONTAINMENT WORKSITE PROCEDURES The Abatement Contractor shall, at a minimum, perform all functions listed below where applicable:
A. Construct full worker and waste decontamination facilities in accordance with the conditions specified in NYC DEP Title 15, Chapter 1 and in accordance with this scope of work where applicable. Decontamination unit shall be located on the parking level and shall be directly connected to the level “A” work area, and indirectly connected to the other work areas via Stair # 2 and Security Elevator #24.
B. Pre-clean and then erect a two stage airlock from the Security Elcvator:^|^lA----'-h. 7 /. barrier wall on floors 8 through 24. Framing for the isolation barrier ^aU'b^”x 4” wood studs, 16” on center. Plywood sheeting shall then be aftw^ '\ outside of the isolation barrier and 2 layers of 6-mil polyethylene sheetiijg shalvsr affixed to the inside. co4 J;, • I
C. Install a minimum of six (6) HEPA filtration units per floor in order tb hNp filter ■ A/ the air in the work area. HEPA filtration and auxiliary air ventila^n/'^ljall 0 conform to Section 2.8 of this specification and shall exhaust/intake exhau^rn'll' 47 location designated by and/or acceptable to the Client. Due to the existing breech" 4
NYC-WTC_000154687
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
No available related records indexed in this group.
NYC-WTC_000128550
Asbestos inspection report notification form submitted to NYC DEP for 102-104 Greenwich Street.
13 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000098577
Contract specifications outlining site decontamination and asbestos disposal procedures for 53 Park Place.
11 shared non-person entities · 1 shared topics · similarity 0.978
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000104853
Facsimile cover sheet transmitting documents regarding environmental work at 102 Greenwich Street.
10 shared non-person entities · 1 shared topics · similarity 0.977
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000112116
NYC DEP emergency notification form documenting an urgent asbestos abatement situation at 250 Vesey Place requiring immediate action.
10 shared non-person entities · similarity 0.976
machine-extracted · confidence unavailable · Check page ↗7 shared non-person entities · 1 shared topics · similarity 0.975
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000127792
NYC DEP Asbestos Project Notification form for abatement activities at a facility in the Phase 1 Decontamination Plan binder.
16 shared non-person entities · similarity 0.975
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000125579
Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.
9 shared non-person entities · similarity 0.975
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000102548
NYC DEP asbestos project notification form for inspection and abatement activities at 114 Liberty Street.
7 shared non-person entities · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000098612
Contract specifications outlining site decontamination and asbestos disposal procedures for 110 Church Street.
12 shared non-person entities · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000128594
Asbestos inspection report notification form submitted to NYC DEP for 102-104 Greenwich Street.
8 shared non-person entities · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155525
Initial draft of the comprehensive scope of work required to safely clean 114 Liberty Street following environmental damage.
15 shared non-person entities · 1 shared topics · similarity 0.971
machine-extracted · confidence unavailable · Check page ↗15 shared non-person entities · 1 shared topics · similarity 0.971
machine-extracted · confidence unavailable · Check page ↗Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000155525
Initial draft of the comprehensive scope of work required to safely clean 114 Liberty Street following environmental damage.
Similarity score 0.974 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Similarity score 0.973 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Similarity score 0.973 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155460
Submission of a preliminary scope of work document for safely cleaning the 114 Liberty Street building.
Similarity score 0.973 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155460
Submission of a preliminary scope of work document for safely cleaning the 114 Liberty Street building.
Similarity score 0.971 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Similarity score 0.971 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Machine-extracted building matches; verify each source. Buildings, never households.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000146129
Correspondence from NYC Corporation Counsel providing comments on excerpts of a draft EPA evaluation report regarding the WTC response.
Cited alongside this record in an Ask answer
NYC-WTC_000105899
Scope of work document dated September 20, 2001, for emergency cleanup at 217 Broadway.
Cited alongside this record in an Ask answer
Cited alongside this record in an Ask answer
NYC-WTC_000110954
Asbestos project notification form for an inspection at 3 World Financial Center.
Cited alongside this record in an Ask answer
NYC-WTC_000115257
Agreement between the City of New York and a landowner for the removal of foreign debris from exterior areas of 212 Pearl Street.
Cited alongside this record in an Ask answer