meter installation contracts is complete in all community boards with the exception of a half
dozen in Brooklyn and Queens, which have relatively few large residential properties. They were
bid in mid-1999, and work began during the first quarter of 2000. “Second round” large meter
contracts for the Bronx, Staten Island and Manhattan also began work in late 2000. In addition to
approximately 61,000 meters installed in multifamily buildings by DEP contractors, another
13,150 have been installed by the private plumbers throughout the city under the Reimbursable
Metering Program.
Meter Refusal Surcharge
DEP mailed warning notices to property owners about the meter refusal surcharge during
October/November 1999 and a second mailing was issued in March 2000 to properties which did
not respond to the first mailing. Meetings with multifamily housing organizations and managers
were held during August-October 1999 and a mailing was sent to major real estate managing
agents in September. The surcharge warning notices led to record numbers of phone calls to
DEP’s Call Centers and submission of meter installation requests by more than 75,000
properties. On July 1 approximately 43,000 surcharge bills were issued to unmetered properties
which had not submitted requests for meter installations. The number of surcharged properties
has since been reduced to approximately 23,000 due to meter installations and cancellation of
surcharges for administrative reasons, particularly issues of defective notification of owners.
DEP conducted negotiations to meter New York Housing Authority (“NYCHA”) buildings
during Summer/Fall 1999. The agreement was finalized during February 2000. Under this
agreement NYCHA will meter its own buildings at its own cost over the next three years and will
cooperate with DEP on a host of water efficiency programs while being provided several years of
“flat-rate” transitional billing. Work on NYCHA’s Staten Island properties has begun and the
contract for the Queens properties has been awarded. Contracts for the properties in the Bronx
were bid during Summer 2001. Commencement of work has been delayed by the relocation of
most of NYCHA’s central staff after September 11, 2001 from offices at 250 Broadway and 75
Park Place.
Unmemorable Properties
Part of the shortfall among both large and small meter installations is associated with the
discovery of properties which are unoccupied, sealed, abandoned or otherwise not consuming
water and therefore, unmeterable. This number is estimated at 5,000 - 7,000 Citywide. 1-2%
of properties have been found with plumbing systems in a state of imminent failure, preventing
meter installation until repairs have been effected. Owners with properties in a state of
“imminent failure” are being informed as part of the surcharge process that DEP will provide
them an additional three months time to complete repairs and install their meter through the
Reimbursable Metering Program. In the case of vacant buildings, DEP recommends a solution