NYC 9/11 Public Portal Document
ACCELERATED WATER METERING
DEP has made progress in meeting this goal; more than 4,050 water meters have
been installed in large buildings in the drainage area by DEP meter installation
contractors since this order was modified. This number is in addition to the 2,641
water meters that had been installed in large buildings by DEP meter installation
contractors in this drainage area at the time this order was modified. Therefore,
more than 6,691 new meters have been installed in the Wards Island area by meter
installation contractors. This total does not include meters installed during
renovations under Local Law 53/1985 or under the Water Board’s Reimbursable
Metering Program (formerly known as the Window of Opportunity Program). These
installations add at least 2,000 additional meters/buildings to the total, based on RMP
installations alone. The most recent meter installation contracts bid cover several
community boards each, so maintaining an exact count of installations in Wards
Island is not as practical as in the past. As of June 1, 2002, there were approximately
59,000 unmetered water/sewer accounts citywide, 92,000 fewer than in July 1999.
Of the unmetered properties, approximately 23,000 are surcharged for failing to
install a meter while approximately 25,000 of the remainder are considered to be
“in process” of being metered since they have submitted requests for DEP contractor
installations. The remainder are vacant/unmeterable, duplicate accounts on a lot,
exempt or otherwise not included. 93% of all water/sewer accounts are metered.
Final completion has been slowed by customers who refuse to have meters installed,
and to some extent by contractual problems. These problems were not considered by
either DEP or DEC at the time the Order was negotiated, yet they have caused delays
in the substantial completion of meter installations.
These problems, and DEP’s responses, include the following:
Small Residential Properties applicant
The first round of all small meter installation contracts was complete for all
neighborhoods in the City by 1998. Completed installations during this “first round”
total approximately 82% of all possible installations. Some properties are
“unmeterable” for physical reasons at the present time, so the completion rate of
“meterable” properties is closer to 93%. Of the remaining properties, 5-10%
probably require the installation of pit meters. These installations were left until now
so that DEP could issue specialized contracts for that work in each borough. The
outdoor pit meter contractors began work in the Bronx and Brooklyn in late
10
NYC-WTC_000144422
OCR can misread numbers and units. Confirm readings against the page image before using them.