Final completion has been slowed by customers who refuse to have meters installed, and to some
extent by contractual problems. These problems were not considered by either DEP or DEC at
the time the Order was negotiated, yet they have caused delays in the substantial completion of
meter installations.
These problems, and DEP’s responses, include the following:
Small Residential Properties
The first round of all small meter installation contracts was complete for all neighborhoods in the
City by 1998. Completed installations during this “first round” total approximately 82% of all
possible installations. Some properties are “unmeterable” for physical reasons at the present
time, so the completion rate of “meterable” properties is closer to 90%. Of the remaining
properties, 5-10% probably require the installation of pit meters. These installations were left
until now so that DEP could issue specialized contracts for that work in each borough. The
outdoor pit meter contractors began work in the Bronx and Brooklyn in late Spring 1998 and in
Queens and Staten Island during late Summer 1998. 2,106 pit meters have been installed in
those four boroughs through July 31, 2001. Indoor small meter contracts began work during the
last quarter of 1998. 57,000 meters were installed through December 31, 2001 and work
continues at a rate of approximately 500 per month.
Over the last few years DEP has been monitoring pilot installations of “single-jet” type water
meters, technology in common use in Europe. The single-jet technology has two advantages
over displacement, turbine and compound meter technologies: 1) smaller size, which allows
meters to fit in more confined locations, and 2) fewer parts, which suggest less of maintenance
burden than compound meters. DEP has begun installing single-jet meters as a substitute for
compound meters in some locations as of Fall 2000 and has been using them as a substitute for
displacement meters in some confined locations where displacement meters cannot fit. In these
cases an outdoor pit installation would otherwise have been the only viable alternative, at greater
cost to DEP and inconvenience to the customer. Waiting for the delivery for single-jet meters
resulted in a delay of at least several hundred and perhaps several thousand small meters in late
2000 which were installed during the first half of 2001.
Large Residential Properties
Large meter installations have been a different story. Among the large meter contracts that are
substantially complete, the average completion rate is only 50%, reflecting primarily a lack of
cooperation from multifamily building owners. Although perhaps 5% of the total large
properties are “unmeterable” for physical reasons, and a somewhat larger number may be delayed
by the need for specialized large meter installations in outdoor vaults, the primary barrier has
been non-cooperation among multifamily residential property owners. The “first round” of large