DEP does not install meters in vacant buildings.
Contracting Issues.
The initial small meter contracts met with the default of a major contractor, setting
the installation schedule back by more than a year and committing limited DEP to
spend additional time resolving problems left incomplete by the original contractor.
This work, which was only finally resolved in 1999, occupied significant staff time
without resulting in a net increase in meters installed.
The bidding of contracts for a final round of small meter installations, and small pit
meter installations was twice delayed by legal challenges from licensed plumber
organizations and/or unsuccessful bidders. These are factors, which have been
beyond DEP’s control and required the rebidding of these contracts, for a delay of
ahnost two years (1996-1998).
There are currently no significant contracting problems.
INTERIM PLANT EXPANSION
This report includes a construction schedule progress analysis for the construction
contracts, and the completion date for obtaining Milestone No. 9, “Obtain Beneficial
Use of Increased Capacity.”
Overall Wards Island Project Status
Milestone No. 9, to Obtain Beneficial Use of Increased Capacity at the Wards Island
Plant was achieved on August 27, 1997. The Interim Plant Expansion Facilities are
currently in operation under the supervision of the Bureau of Wastewater Pollution
Control.
Modified Order on Consent
The New York City Law Department, in a letter dated June 19,1997 to NYSDEC,
formally requested a modification of Milestone No. 9 to extend the June 23,1997
milestone date to August 29,1997. The NYCDEP, in a letter dated September 9,
1999, confirmed that the subject milestone was met on August 27,1997, the
modified milestone date.