The main issue which is presently being pursued in an effort to complete all construction and
close out of this phase, is resolution of Fire Department deficiencies listed against the New
Return Sludge Pump Station and the New Fuel Oil Storage Facility.
Conclusion
All nine Consent Decree Milestone dates have been achieved. The overall construction work at
Wards Island is approximately 99% complete. The remaining work to complete the New Fuel
Oil Storage Facility which is not part of the Consent Order, is now projected to be completed by
June 30, 2002.
Please refer to the attached Attachment No. 1 (Master Summary Schedule).