vi. residents with special needs or medical conditions that may be aggravated by
exposure to airborne contaminants (DEP notification); or
vii. other circumstances that may require deviation from the procedures specified
in the scopes of work for the cleaning and monitoring contracts.
e. In consultation with EPA, the Project Monitor will make a determination of the
appropriate Cleaning Contract Scope ofWork (i. e. Scope A or B) to be implemented.
This determination is to be made based on the descriptions included in the Cleaning
Contract Scope of Work and best professional judgement.
Deliverables
All deliverables shall be provided in the EPA Indoor Air web database via F2L or an agreed
upon alternative electronic format or website approved by EPA within 24 hours of activity.
The Project Monitor shaU record all pre-cleaning and pre-sampling inspection information in
the EPA Indoor Air database or using an agreed upon electronic format. This information
shall include, but is not limited to, WTC debris present on building exterior (Y/N), type of
HVAC system (central, individual or none), HVAC impacted (Y/N), occupant present (Y/N),
written access obtained (Y/N), space occupied (Y/N), dust present (low/high), mold present
(Y/N), peeling /flaking/chalking paint present (Y/N), suspected ACM present (Y/N)
residential use (commercial/residential), residents with special needs, cleaning method (Scope
A or B). Dates and times shall be associated with all activities including start and finish date.
3. In the event that mold or flaking, peeling or chalking paint is observed is observed on
building components (walls, support beams, ceiling tiles, HVAC systems) in areas where
work has been requested, the Monitoring Contractor will notify EPA and fax a written
request for assistance in evaluating potential health hazard to NYC DOH at 212-442-3378.
Cleaning will not proceed in areas where mold or flaking, peeling or chalking paint is
observed until potential hazards are evaluated and addressed as necessary.
Deliverables
The Project Monitor shall record if mold or flaking, peeling or chalking paint is present and
notify the NYCDOH and EPA. This information shall be provided via EPA Indoor Air web
database or an agreed upon alternative electronic format or website approved by EPA within
24 hours of activity.
4. In the event that suspected asbestos containing material (ACM) from sources other than the
WTC is observed, the Monitoring Contractor will notify EPA and fax written notification to
DEP at 718-595-4544 . Cleaning will not proceed in areas where such suspected ACM is
observed until instructed otherwise.
Deliverables
The Project Monitor shall record if suspected ACM from sources other than the WTC or
5