on TO: Deputy Mayor
>17.tAV'L lI04ditW,
o,,,tl{iit:rert' . FROM: Joel A.
DATE: March 1.
RE: New Croton Darn Spillway Bridge
I would like to update you on the status of the closure of the New
Croton Darn Spillway Bridge and provide recommendations on our next steps.
The Bridge remains closed to all traffic, When the recent movement of the
Bridge span supports was discovered, DEP was already prepared to proceed
with a repair of the Bridge, Thus DEP has both design and construction
consultants currently under contract. The design contractor has recommended
a short-term repair and the long-term replacement of the span. I am moving
on the following actions:
1) Have the existing design contractor. Hardesty and Hanover, complete
designs for the short-term repair. The repair would be completed either by
• McNamee, the current construction contractor, or via emergency bidsiif
McNamee declines to undertake the work. The repair would cost about
$200,000 if done by McNamee; if an emergency contract is necessary the
cost could be significantly higher. The work would take approximately
two months, after which time the Bridge would be re-opened with a 10-ton
limit (the weight limit of the Bridge prior to its closing).
2) Direct Hardesty and Hanover to design a new Bridge span via change
order to their existing contract. Approximate cost of design is $450,000.
3) Construct a new Bridge span under a new contract. Hardesty and Hanover
has recommended that z construction contractor be on board by the end of
2002. Cost of the replacement is expected to be 53 million. Construction
will take 18 months and require re-closing the Bridge for approximately
• six months.
The other outstanding issue pertains to detouring vehicular traffic
around the bridge. We have consulted with the Towns of Cortlandt. New
Castle, and Ossining. the towns affected with respect to agreeing on a detour
for vehicles exceeding the weight limit of the pertinent roads. Because of
ongoing repairs to the Cortlandt road, the detour has been temporarily
lengthened. When Cortlandi completes road repairs next week, we will
shorten the truck detour as much as possible.