EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
Mr. Pat Evangelista— Response to Comments
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— August 11, 2005
19. Added s noted.
20. No torching is to be conducted. References deleted.
21. Edited as noted.
22. Edited as noted.
23. No elevators exist, none to be utilized. Reference deleted.
24. A map showing routes to NY Downtown Hospital has been attached. Floor
plans with emergency egress routes have been added. Section 2.8.3 describes
topics to be discussed in Safety Meetings. Section has been updated to note
that safety equipment will be stored in the CRZ.
25. The reference should be to Section 2 of this HASP, not Section 3 of the Work
Plan. The HASP has been edited to reflect this. A contacts list has been added
to the Appenices.
26. Revised as noted.
27. Revised as noted.
28. Edited as noted.
29. Deleted as noted.