• As the Contractor SSM proceeds to the accident scene, communications channels shall be
opened and kept on standby until the Contractor SSM has surveyed the scene and
performed a primary survey of the victim.
The Contractor SSM shall provide emergency action guidance consistent with the injury
and shall relay the appropriate information to the site person meeting the EMS.
Depending on the nature of the injury and the location at which the injury occurred, the
Contractor SSM shall determine whether the person can be moved or whether the EMS
team will need to come into the work area to assist the victim. Should the victim be
injured in the Exclusion Zone, all appropriate life-saving methods shall be exercised in
that area before attempting decontamination of the victim. The extent of emergency
decontamination performed shall depend on the severity of the injury or illness and the
nature of the contamination. If the emergency is such that emergency decontamination
cannot be performed safely, the victim shall be given necessary first-aid treatment
and wrapped in a blanket prior to transportation by EMS. If heat stress is a factor in a
victim's injury/illness, all protective clothing shall be removed from the victim
immediately.
Non-Life-Threatening Incident
Should it be determined that no threat to life is present, a co-worker will assist the injured
person and contact the Contractor SSM as soon as reasonably possible. Should the victim
be injured in the Exclusion Zone, a rapid decontamination consisting of Tyvek, glove and
respirator removal shall be performed in the Contamination Reduction Zone prior to
initiation of medical assistance. For all non-life-threatening injuries, all medical
assistance shall be provided in the Support Zone to reduce the spread of contamination to
medical personnel or equipment.
2.13.5 Bloodborne Pathogens
When an emergency occurs that involves the potential for contact with bodily fluids,
personnel shall use procedures and PPE that minimize the potential for exposure.
All personnel who provided direct support to an injured person shall participate in a post-
incident exposure review during which their role in the event and the potential for contact
with bodily fluids shall be evaluated. The information relating to exposure shall be
documented for each individual. The procedures for the post-exposure consultation
identified in the OSHA Bloodborne Pathogens Standard (29 CFR 1910.1030) shall be
followed.
All personnel on-site shall receive awareness training concerning Bloodborne Pathogens
(BBP) and the procedures to be followed to respond to emergencies that occur on-site.
This awareness training shall be provided by each Subcontractor prior to the initiation of
work activities and when new employees are introduced to the Site. In addition, each
Subcontractor must have a BBP plan.
•
The Copper Group —133-135 Greerw(ch Street & 21-23 Thames Street
Atitek Project 05=0710 - Phase I HASP 6-&05 rase 35 of 40