130 Cedar Street July 15, 2004
Selective Demottion and Façade Restoration Koenen Associates
2. Architect will prepare and issue a Certificate of Substantial Completion,
containing:
a. Date of substantial completion.
•
b. Punch list of items to be completed or corrected.
c. The time within which Contractor shall complete or correct work
of listed items.
d. Date or time Owner will assume possession of work or
designated portion thereof.
D. Contractor. Complete work listed for completion or correction, within designated
time.
1.05 FINAL INSPECTION
A. Contractor shall submit written declaration to Owner and Architect that:
1. All aspects of Contract Documents have been complied with.
2. All items on substantial completion punch list have been completed.
3. All tools, construction equipment, and surplus materials have been
removed from site.
B. The Owner, Architect and Contractor will make final inspection to ensure
completion of all contract requirements.
C. When the Architect considers that work is finally complete In accordance with •
Contract Document requirements, the Architect will process close-out documents
prior to issuance of final Certificate of Payment.
1.06 OPERATING AND MAINTENANCE INSTRUCTIONS
A. Three (3) bound sets of operating and maintenance instructions covering
completely the operation and maintenance of all equipment furnished under the
Contract shall be delivered to the Owner. These shall include operating
sequence and flow diagrams of all systems. Three (3) sets lubricating charts
of
and manuals for each item of equipment shall be furnished.
B. Upon completion of the work and at a time designated, a competent engineer
shall be provided for a sufficient period to instruct representatives of the Owner In
the operation and maintenance each piece of equipment and of equipment and
of
of each system as a whole.
C. In addition, furnish to the Owner in three (3) sets of 8-which shall include, for each
piece of operating equipment (electric or otherwise powered), the name,
address, and telephone number of the firm or organization who are authorized by
the manufacturer of the Installed equipment, to service and maintain the
equipment as the need may arise within twenty-four (24) hours when summoned
by the Owner.
1.07 PROJECT RECORD DOCUMENTS
•
Contract Close-Out 01700-2
NYC-WTC 000125146