SECTION 01700
CONTRACT CLOSE-OUT
PART 1.00 - GENERAL
1.01 GENERAL REQUIREMENTS
A. Work of this Section, as shown or specified, shall be in accordance with the
requirements of the Contract Documents.
1.02 WORK INCLUDED
A. Work of this Section includes all labor, materials, equipment and services
necessary to complete the contract close-out, including but not limited to, the
following:
1. Punch list.
2. Keys and maintenance kits.
3. Warranties and guarantees.
4. Operating and maintenance Instructions.
5. Project record documents.
6. Certificate of Occupancy.
7. Equipment system demonstration.
1.03 RELATED WORK
A. Submittals - Section 01300.
B. General Conditions.
1.04 PUNCH LIST
A. Contractor
1. Submit written declaration to Architect that project is substantially
complete.
2. Submit list of items to be completed and corrected (punch list).
B. Owner, Architect and Contractor will make preliminary Inspection after receipt of
Contractor's declaration and punch list.
C. Should Owner and Architect consider that work is substantially complete:
1. Architect will add to the punch list Items to be completed or corrected, in
addition to those items listed by the Contractor, as determined by the
inspection.
•