NYC 9/11 Public Portal Document
130 Cedar Street July 15, 2004
Selective Demolition and Façade Restoration Koenen Associates
SECTION 01400
TESTING AND INSPECTION
•
PART 1.00 - GENERAL
1.01 GENERAL REQUIREMENTS
A. Work of this Section, as shown or specified, shall be in accordance with the requirements
of the Contract Documents.
1.02 WORK INCLUDED
A. Work of this Section includes all labor, materials, equipment and services necessary to
complete the testing and inspection requirements as specified herein.
1.03 RELATED WORK
A. Requirements for Testing and Inspection shall be described In various Sections of these
Specifications. Where no testing and Inspection requirements are described but the
Owner decides that it is required, the Owner may require additional testing and Inspection
to be performed at his own expense.
B. Work Not Included
1. Unless otherwise noted in this Section or other Section of work, the Owner will
select a pre-qualified independent testing laboratory and inspection professional.
2. Unless otherwise noted in this Section or other Sections of work, the Owner will
•
pay for all initial services of the testing laboratory and inspection professionals
as further described in Article 2.01 of this Section of these Specifications.
1.04 QUALITY ASSURANCE
A. The testing laboratory will be qualified to the Owner's approval in accordance with ASTM
E-329- 70 "Recommended Practice for Inspection and Testing Agencies for Concrete
and Steel Used in Construction.
B. Testing, when required, will be in accordance with all pertinent codes and regulations and
with selected standards of the American Society for Testing and Materials.
1.05 PRODUCT HANDLING
A. Promptly process and distribute all required copies of test reports and related instructions
to ensure all necessary retesting and/or replacement of materials with the least possible
delay in progress of the work.
PART 2.00 - PRODUCTS
2.01 PAYMENTS FOR TESTING AND INSPECTION SERVICES
A. Initial Services: The Owner will pay for all initial and inspection services.
B. Retesting; When initial tests and inspections Indicate non-compliance with local Codes
and the Contract Documents, all subsequent retesting occasioned by the non-
S Testing and Inspection 01400-1
NYC-WTC 000125127
OCR can misread numbers and units. Confirm readings against the page image before using them.