130 Cedar Street July 15, 2004
Selective Demolition and Facade Restoration Koenen Associates
and dates reviewed submittals will be required from Architect. Indicate decision data for
selection of finishes.
G. Indicate delivery dates for Owner furnished products and Products identified under
Allowances.
1.06 REVISIONS TO SCHEDULES
A. Indicate progress of each activity to date of submittal, and projected completion date of
each activity.
B. Identify activities modified since previous submittal, major changes in scope, and other
Identifiable charges.
C. Provide narrative report to define problem areas, anticipated delays, and impact on
Schedule. Report corrective action taken, or proposed, and its effect including the effect
of changes on schedules of separate contractors.
1.07 SUBMITTALS
A. Submit initial Schedules within 5 days after date of Owner-Contractor Agreement. After
review, resubmit required revised data within ten days.
B. Submit revised Progress Schedule with each Application for Payment.
C. Submit one opaque reproduction and one reproducible transparency.
1.08 DISTRIBUTION
A. Distribute copies of reviewed Schedules to project site file, Subcontractors, suppliers,
and other concerned parties.
B. Instruct recipients to promptly report, In writing, problems anticipated by projections
indicated in Schedules.
PART 2.00 - PRODUCTS
(Not Used)
PART 3.00 - EXECUTION
(Not Used)
END OF SECTION
[1
Progress Schedules 01310-2