SECTION 01310
PROGRESS SCHEDULE
PART 1.00 - GENERAL
1.01 GENERAL REQUIREMENTS
A. Work of this Section, as shown or specified, shall be in accordance with requirements of
the Contract Documents.
1.02 WORK INCLUDED
A. Work of this Section includes all labor, materials, equipment and services necessary to
complete the progress schedule as specified herein, including, but not limited to, the
following:
1. Format.
2. Content.
3. Revisions to schedules.
4. Submittals.
1.03 RELATED WORK
A. Summary of work - Section 01010.
le 1.04
B.
FORMAT
Submittals - Section 01300.
A. Prepare Schedules as horizontal bar chart with separate bar for each major portion of
Work or operation, identifying first work day of each week.
B. Sequence of Listings: The chronological order of the start of each item of Work.
C. Scale and Spacing: To provide space for notations and revisions.
1.05 CONTENT
A. Show complete sequence of construction by activity, with dates for beginning and
completion of each element of construction.
B. Identify each item by Specification section number.
C. Identify work of separate stages and other logically grouped activities.
D. Provide sub-schedules to define critical portions of the entire Schedule.
E. Show accumulated percentage of completion of each Item, and total percentage of Work
completed, as of the first day of each month.
F. Provide separate schedule of submittal dates for shop drawings, product data, and
samples, including Owner furnished products and Products Identified under Allowances,
•