NYC 9/11 Public Portal Document
130 Cedar Street July 15, 2004
Selective Demolition and Façade Restoration Koenen Associates
material, including the following procedures:
1. Determine and verify all field dimensions and conditions, materials, catalog
numbers and similar data.
2. Coordinate as required with all trades and with public agencies involved.
3. Secure all necessary approvals from public agencies and others and signify by
stamp, or other means, that they have been secured.
4. Clearly indicate all deviations from the Contract Documents.
B. Unless otherwise specifically permitted by the Architect, make all submittals in groups
containing all associated items; the Architect may reject partial submittals as not
complying with the provisions of the Contract Documents.
END OF SECTION
•
Submittals 01300-7
NYC-WTC 000125124