I SCOPE OF WORK
' 53 PARK PLACE
The abatement work to be performed under this contract consists of the complete removal and
disposal of all asbestos contaminated dust, the decontamination of all surfaces, including
mezzanine level, residential units, tenant's possessions located within residential units, common
areas, corridors, and storage areas. All decontamination and disposal shall be carried out in full
I and strict accordance with all applicable Federal, State and local codes, rules and regulations and
with the Contract Documents. All work shall be performed under modified full containment
procedures in accordance with New York City Department of Environmental Protection
Memorandum "Cleanup Of Asbestos Containing Materials" dated September 14, 2001 and the
Contract Documents.
The Contractor shall provide all union labor, materials and equipment to complete the work as
specified in or contemplated by the Contract Documents, including but not limited to the
I following:
1. The filing of all required notifications and variances, including the payment of all fees
I charged by all regulatory agencies.
2. Work area preparation.
I 3. General protection.
4. Isolation and barrier construction.
I 5. Removal of all asbestos contaminated dust and decontamination of all surfaces within the
limits of this contract.
I 6. Provide and install personnel and waste decontamination facilities.
7. Packaging, transportation and the legal disposal of asbestos contaminated waste.
8. Repair or replacement, to the Owner's satisfaction, of any existing finishes, construction
or other building components to remain which are damaged during the prosecution of the
I work.
9. Maintain complete inventory and final disposition of all contaminated items removed
I from residential units by apartment number, including time and date of removal.