TECHNICAL REQUIREMENTS
I 1.0 All personnel engaged in the cleaning shall be NYS and NYC licensed asbestos handlers
and/or supervisors.
1. The Contractor shall provide and install a personnel and waste decontamination
unit in accordance with the Contract Documents.
2. All personnel shall wear personnel protective equipment (PPE) while in the work
I area.
3. The Contractor shall provide and install isolation barriers between all
contaminated and clean areas.
' 4. Each floor shall be considered a separate work area.
5. Each contained work area shall have a triple curtained entranceway constructed of
six mil poly.
6. REPA equipped air filtration devices shall be utilized during decontamination
procedures at locations to be determined at the direction of the Consultant.
I
EPA WASTE GENERATOR LABELING
All contaminated waste disposed of by Contractor shall identify Lions Head 53 Development
LLC as the waste generator. Labels shall indicate waste was generated by World Trade Center
incident.
All potentially contaminated, or contaminated items returned to tenants shall identify the tenant
or the owner of said item(s) as the waste generator. Such items include, but are not limited to,
clothing, mattresses, box springs, bed clothes, furniture, electronics or any other items.
I
I
I
7!
I S-2
NYC-WTC 000098582
OCR can misread numbers and units. Confirm readings against the page image before using them.