SECTION 02082
In specific areas where the window components or the exterior surfaces of the beams and/or
columns were tested and determined to be coated with lead-based paint, the Contractor shall be
directed by the Construction Manager, to employ measures to prevent exposure to the building
occupants and workers to lead contaminated dust, debris or paint chips. Refer to the f.,ead-Based
Paint Specification for details.
B. The phasing and scheduling of work for this project shall be coordinated with and approved by
the Resident Engineer and Eacility Manager. The Resident Engineer and Eacility Manager will
make the final determination on all issues under this Contract covered by this Specification.
C. Contractor is to provide all labor, materials, equipment, services, testing, appurtenances, permits
and agreements necessary to perform the work required for the abatement of ACM as required
by these contract documents. All work shall be performed in accordance with this Specification,
EPA regulations, OSHA regulations. New York City Eocal Eaw 70, Title 15, Chapter 1 RCNY,
New York State Industrial Code 56, NTOSH recommendations, and any other applicable federal,
state or local government regulations. Whenever there is a conflict or overlap of the above
references the most stringent provisions are applicable.
D. These Eacilities are under the jurisdiction of the New York City Board of Education and
provides services from 7:00 a.m. to 5:00 p.m. The phases and hours intended for the scheduling
of the work for this asbestos abatement project has to be coordinated with the Construction
Manager, Board of Education, District area representative. Schools principal or his/her
representative, UET representative and the Facility Manager (School Custodian). Unless
indicated elsewhere in these Specifications, all work shall be accomplished during regular
working hours. It is the Contractor's responsibility to plan and schedule the work of this Contract
with the approval and consent of the Construction Manager and Facility Manager.
The Contractor shall establish his working schedule in a way that avoids interference or conflict
with the normal functioning of the facility. Working in the evenings and weekends shall be
allowed and authorized by the Commissioner and shall be done at no additional cost to the
Construction Manager.
E. The intent of this Specification section is to ensure that Contractor is responsible for the
following:
1. Abatement of all ACSM,
9 Cleaning and decontamination of the entire affected area,
3. Demolition that may be required to access ACSM in each area; Contractor shall dispose
of all debris associated with demolition activities as asbestos waste.
4. Removal and disposal of any other ACM found that will be directly affected by the scope
of work.
5. Provide all scaffolding, platform installation, equipment, tools, transportation and any
other equipment required and/or necessary to complete all work described in the Contract