(c) Explosives packaged in cardboard tubes that can be coupled
into a continuous column as they are placed in the hole can be used in
place of the string loads. Such long narrow cartridges (i.e. 1 by 36 in.
and 3/4 by 24 in.) are becoming prevalent in current practice. They
give better powder distribution and lessen the chances of crushing rock
at the perimeter of the borehole. Loading time is also reduced con
siderably and contractors should be encouraged to use them.
(d) Hole depth in presplitting is limited by the difficulty in drill
ing accurately alined holes which, in turn, is dependent on the quality
of the rock mass. When more than one level of prespiitting is neces
sary, a 1-ft bench offset is usually left between lifts by the drill setup.
Presplit holes are commonly 25 to 40 ft deep. Holes exceeding 40 ft
should not be permitted unless it can be demonstrated that accurately
alined holes will be achieved. It is essential that the holes start and
remain in the presplit plane; therefore care must be exercised, first,
in establishing the trace of the plane on irregular ground surfaces and,
second, in maintaining the correct inclination and direction of the holes.
Templates are often useful in achieving correct drill setups. ’
(e) Presplit blastholes loaded with gelatin dynamite can be
either wet or dry. Wet holes tend to increase occurrences of bridging
of stemming material such as drill cutting, overburden, or clay. Only
clean stone chips or screened gravel should be used. Either angled
or vertical holes may be used, as long as they are kept parallel by
using a clinometer. The deviation of holes from the designed plane
should not be greater than 6 in. at the bottom and for close hole spac
ing should be much less.
(2) R£lation_to_Main_B]^^^ Presplitting and primary blasting
are sometimes performed in one operation with the pre split and pri
mary holes drilled and loaded at the same time. Delays of 100 to 200
msec separate the two blasts. This method reduces time needed to
set up drilling equipment. Usually, however, the line of presplit holes
is drilled ahead of the main blast pattern as shown in Fig. 5-20. The
final row in the primary pattern is commonly kept 3 to 4 ft from the
presplit row. A delay pattern designed to provide maximum relief
to the main blastholes nearest the presplit line should be used for the
primary blasting. Delays sequenced parallel to the presplit may
reduce damage in the permanent wall (see d(3)(c) below). The presplit
surface should be kept about half the length of the primary pattern ahead
of the main blast area so that subsequent blasts can be altered to fit
changing rock conditions. Lighter loading of holes of the main charge
near the presplit may reduce damage to the wall (d below). In special
cases where the confinement (burden) is not sufficient, smooth blast
ing may be applicable (b below).