NYC 9/11 Public Portal Document
Asbestos Abatement
successfully completed in a timely fashion at least five projects
similar in scope and type to the required work (i.e., asbestos
abatement projects using the techniques specified in this contract.)
2. For each project submitted to meet the requirements set forth in
Item 1 above, the Contractor or Subcontractor must complete the
Qualification Form set forth in the Bid Booklet, specifically indicating
the following information.
a. Name of Contractor
b. Name and location of the project
c. Name, title and telephone number of the City or an City's
representative who is familiar with the Bidder's work on the
project
d. Brief description of the work completed
e. Indicated whether the work was performed as a prime or
subcontractor
f. Amount of the contract or subcontract
g. Date of completion
R. Asbestos Abatement License: Contractor or Subcontractor performing the work of
this section must, for the past three years, have been licensed for asbestos
abatement work by the New York State Department of Labor. Contractor must
submit a copy of such valid asbestos abatement licenses.
S. Compliance with Experience Requirements: Contractor is advised that no
Subcontractor will be approved for the performance of asbestos abatement work
hereunder unless it demonstrates compliance with the experience requirements set
forth above. Compliance with such experience requirements will be determined
solely by the City.
T. In the event that the bid submission is a joint venture, at least one firm in the joint
venture must meet the above described experience requirements.
U. Insurance Requirements: The asbestos contractor must proved asbestos liability
insurance in the following amount: 1 million dollars per occurrence, 2 million
dollars aggregate (combined single limit). The City of New York shall be named
as an additional insured on such insurance policy.
V. Throughout the specifications, reference is made to codes and standards which
establish qualities and types of workmanship and materials, and which establish
CAPITAL PROJECT NUMBER PO79201K 02081-9
100: CONTRACT DOCUMENTS REV. May 3,2000
- 9 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_0 06631258
NYC-WTC_000416770