Asbestos Abatement
pressure rating greater than the maximum pressure of the water
distribution system to provide water into each Work Area and to each
Decontamination Enclosure Unit. Provide fittings as required for
connection to existing wall hydrants or spouts, as well as temporary water
heating equipment, branch piping, showers shut-off nozzles and
equipment.
3. Water Heater: Provide UE rated 40-gallon electric water heaters to supply
hot water for Personal Decontamination Enclosure System Shower.
Activate from 30 Amp Circuit breakers located within the
Decontamination Enclosure subpanel. Provide relief valve compatible
with water heater operations, pipe relief valve down to drip pan at floor
level with type 'L' copper piping. Drip pans shall be 6-inch deep and
securely fastened to water heater. Wiring of the water heater shall comply
with NEMA, NECA, and UE standards.
Q. Electrical Service:
1. General; Comply with applicable NEMA, NECA and UE standards and
governing regulations for materials and layout of temporary electric
service.
2. Temporary Power: Provide service to decontamination unit subpanel with
minimum 60 AMP, two pole circuit breaker or fused disconnect connected
to the building's main distribution panel. Subpanel and disconnect shall be
sized and equipped to accommodate all electrical equipment required for
completion of the work.
3. Voltage Differences: Provide identification warning signs at power outlets
that are other than 110-120 volt power. Provide polarized outlets for plug
in type outlets, to prevent insertion of 110-120 volt plugs into higher
voltage outlets. Dry type transformers shall be provided where required to
provide voltages necessary for work operations.
4. Ground Eault Protection: Equip all circuits for any purpose entering Work
Area with ground fault circuit interrupters (GECI). Eocate GECIs exterior
to Work Area so that all circuits are protected prior to entry to Work Area.
Provide circuit breaker type ground fault circuit interrupters (GECI)
equipped with test button and reset switch for all circuits to be used for
any purpose in Work Area, decontamination units, exterior, or as
otherwise required by NEC, OSHA or other authority. Eocate in panel
exterior to Work Area.
5. Power Distribution System: Provide circuits of adequate size and proper
characteristics for each use. In general run wiring overhead, and rise
vertically where wiring will be least subject to damage from operations.
CAPITAL PROJECT NUMBER PO79201K 02081-51
100: CONTRACT DOCUMENTS REV. May 3,2000
-51 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631300
NYC-WTC_000416812
OCR can misread numbers and units. Confirm readings against the page image before using them.