Asbestos Abatement
inside/5 samples outside for Earge Projects and three samples inside/three
samples outside for Small Projects). In addition to the five sample inside/five
sample outside minimum for Earge Projects, one additional representative area
sample shall be collected inside and outside the work area for every 5,000 square
feet above 25,000 square feet of floor space where ACM has been abated.
J. Post-abatement clearance air monitoring for Small Projects solely employing
glove-bag procedures is not required unless one or more of the following events
occurs. In such cases, post-abatement clearance air monitoring procedures shall
be followed. The events requiring post-abatement clearance air monitoring are:
1. The integrity of the glove-bag was compromised,
2. Visible emissions are detected outside the glove-bag, and/or
3. Ambient levels exceed 0.01 f/cc during abatement.
K. Monitoring requirements for other than post-abatement clearance air monitoring
are as follows:
1. The sampling zone for indoor air samples shall be representative of the
building occupants' breathing zone.
2. If possible, outdoor ambient and baseline samplers should be placed about
6 feet above the ground surface in reasonable proximity to the building
and away from obstructions and drafts that may unduly affect airflow.
3. For outdoor samples, if access to electricity and concerns about security
dictate a rooftop site, locations near vents and other structures on the roof
that would unduly affect airflow shall be avoided.
4. Air sampling equipment shall not be placed in comers of rooms or near
obstructions such as furniture.
5. Samples shall have a chain of custody record.
L. Area air sampling during abatement shall be conducted as specified in the
following documents except as restricted or modified herein:
1. Measuring Airborne Asbestos Pollowing an Abatement Action, US EPA
document 600/4-85-049 (Nov., 1985);
2. Guidance for Controlling Asbestos-Containing Materials in Buildings; US
EPA Publication 560/5-85- 024 (lune, 1984);
3. Methodology for the Measurement of Airborne Asbestos by Electron
Microscopy US EPA Contract No. 68-02- 3266;
CAPITAL PROJECT NUMBER PO79201K 02081-43
100: CONTRACT DOCUMENTS REV. May 3,2000
- 43 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_0 06631292
NYC-WTC_000416804
OCR can misread numbers and units. Confirm readings against the page image before using them.