Asbestos Abatement Specifications - 130 Liberty, North Side
Acceptance Criteria; Decontamination of the work site meets the
requirements of this test when every work area sample indicates an
airborne concentration of fibers of less than 70 structures per millimeter
squared. If any sample is above this clearance level, then the
1
decontamination is incomplete and the work area shall be re-cleaned.
2.13 PREVENTION OF RECONTAMINATION
To deter recontamination of the north side area after successful clearance testing,
the contractor shall confirm (and replace) all critical barriers along the north
barrier wall. Further, the tunnel from car #24 to the north sid'eharnerwall shall
remain in place. y ' ' -*
3. GENEIUL CONDITIONS
^4,) e cla’--'.
A. All removal shall be performed utilizing feH—eoatainment/g-ross Ternoval
procedures as required by NYCDEP Title 15, NYSDOL ICR 56 and in
accordance with all other applicable federal, state and local regulations. All ACM
shall be wetted using amended water prior to removal.
B. Water hookups to be provided by the Abatement Contractor and to be coordinated
with the Client.
C. Contractor shall deliver sufficient ground fault interrupt service (GFI) panels to
the site. Panels shall meet the requirements of applicable provisions of the
National Electric Code. The panels shall be connected by the on-site electrical
contractor. The on-site electrical contractor shall be responsible for any and all
standby electrician costs as required by the Scope of the Work. The contractor
shall assure that all full-containment areas shall be equipped with sufficient
temporary GFI electrical and hghting installation to accommodate the Scope x>T
the Work as indicated in this document, including all air sampling outlets.
D. The Abatement Contractor shall provide temporary lighting in all Work Areas,
decontamination units and staging areas for the duration of the project shall
maintain temporary lighting and circuits. All temporary lighting shall be GFI
service. In addition, all air sampling locations shall be provided with temporary
lighting and power as per the Environmental Consultant’s requirements.
E. All waste to be transported shall be doubled-bagged and properly labeled.
G;\2002\220201 130 Liberty DEUTSCHE BANK acm\220201 North Spec.doc. 10