NYC 9/11 Public Portal Document
TO: Commissioner Miele 718-595-3S25 CC: First Deputy Commissioner Chapin 718-595-3557 Deputy Commissioner Avaltroni 718-595-4544 Deputy Commissioner Greeley 718-595-5342 Deputy Commissioner Lopez 718-595-6950 Deputy Commwsioner Principe 914.741-0348 FROM: Paul Bennett W17-769-1282 RE; WTC Daily Report for 10/22/01 DATE: Oct. 22, 2001 via FAX Summan of outstanding activities for 10/22/01.
FDNY HazMat has offered to speak to DEP Upstate HazMat regarding resp[onse to suspicions package protocol. Mike; Please let me know if you want to take FDNY up on their offer?
OEM requests assistance in design and installation of storm water runoff form their new HQ. Update; BWSO to assist OEM has requested assistance in design and installation ofa storm water management system for their newfacility being built in Gravesend, BK (W13 St & Ave Z). Apparently. a large parking lot is being constructed and OEM has askedfor assistance in installing catch basins / storm drains, /s this something for DEP or DDC?
Health and Safely meeting EPA detected low levels of Freon 22 at two locations. FYI - EPA detected Freon 22 at concentrations up to 48 ppm on the pile at the North Tower and ^6 WTC locations.
Quality of water to be / is being pumped from the WTC Update; EPA requested DEP HazMat to conduct the .sampling, M, Fawzy to make arrangements. Additional sampling and analysis of the water in the basement will be conducted by EPA. Industrial Waste is working with DDC and their contractor on developing a plan. DDC did not idsntijy when dewatering would begin. NYSDOH Jitn Covey and NYSDEC questioned the quality of the water to be / is being pumped outfrom the basements of the WTC andfrom the PA tunnel and into the sewers. DEC has indicated that they are willing to take the lead on this issue (plan, protocol and ultimate disposal), but they need NYC to askfor such assistance.
Dust Control Update: Dust control continues to be problematic despite my efforts in speaking to contractor foremen on site, discussions at the 9:00 AM DDC/Coatractor meeting and the 6:00 PM Health and Safety Meeting. I’ve begun to document dust suppression activities in support of my comments made at the meetings,
Manpower hours for EMRP on 10/22/01: Paul Bennett Pier 92 11:00 AM-11:00 PM 12hrs Frank Vazquez Command Bus off Robert Kepich Command Bus 12:00 PM- 12;00 AM 12 hrs Joe Scafidi Command Bus 12:00 AM-12:00 PM 12 hrs -end-
TO’d 1003 33 730
CITY_21MC100_011098861
NYC-WTC_000307984
OCR can misread numbers and units. Confirm readings against the page image before using them.
Related records
Browse subjects →Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
Same-box records
NYC-WTC_000247487
Update on OEM storm water runoff system design and installation at Gravesend facility.
10 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000307985
Summary of stormwater and drainage system needs for OEM facility near Gravesend.
7 shared non-person entities · 1 shared topics · similarity 0.970
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000209380
Memo requesting DEP assistance for storm water runoff design and installation at the OEM new facility in Gravesend.
8 shared non-person entities · 1 shared topics · similarity 0.967
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000247486
Summary of outstanding activities including storm water management at new OEM HQ site.
8 shared non-person entities · 1 shared topics · similarity 0.958
machine-extracted · confidence unavailable · Check page ↗Filed elsewhere
NYC-WTC_000154487
Daily report noting OEM requests for assistance in designing and installing a storm water management system.
8 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000455925
Daily OEM report detailing stormwater, site safety, and sampling planning actions.
8 shared non-person entities · 1 shared topics · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000455462
Daily WTC operations briefing and stormwater/ID requests for new HQ.
8 shared non-person entities · 1 shared topics · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000154442
Summary of outstanding activities for 10/10/01 including cell phone tower placement investigation and pending technical authority site investigation report.
8 shared non-person entities · 1 shared topics · similarity 0.948
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000154444
Memo summarizing daily activities including a FEMA meeting request on October 11, 2001.
6 shared non-person entities · 1 shared topics · similarity 0.944
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000154438
Memo summarizing daily activities including a stray current investigation site visit on October 9, 2001.
5 shared non-person entities · 1 shared topics · similarity 0.942
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000154446
Memo summarizing WTC daily activities including water access requests and a FEMA meeting on demolition permits.
6 shared non-person entities · 1 shared topics · similarity 0.934
machine-extracted · confidence unavailable · Check page ↗More like this page
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000247487
Update on OEM storm water runoff system design and installation at Gravesend facility.
Similarity score 0.993 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000154487
Daily report noting OEM requests for assistance in designing and installing a storm water management system.
Similarity score 0.990 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000455925
Daily OEM report detailing stormwater, site safety, and sampling planning actions.
Similarity score 0.987 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000455462
Daily WTC operations briefing and stormwater/ID requests for new HQ.
Similarity score 0.987 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000154484
Memo summarizing daily activities including an OEM request for storm water system assistance on October 19, 2001.
Similarity score 0.985 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Others also read
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Similar indexed content
NYC-WTC_000247487
Update on OEM storm water runoff system design and installation at Gravesend facility.
Similar indexed content
Daily report noting OEM requests for assistance in designing and installing a storm water management system.
Similar indexed content
NYC-WTC_000455925
Daily OEM report detailing stormwater, site safety, and sampling planning actions.
Similar indexed content
NYC-WTC_000455462
Daily WTC operations briefing and stormwater/ID requests for new HQ.
Similar indexed content