NYC 9/11 Public Portal Document
Asbestos Inspection Report
Premise No. Inspection Date:
130 Liberty Street 02/18/09
Floor Zip Borough Block Lot Squad # Badge #
Various_________ 10006 1 54 1 1 A062
Inspector Building Type Basis of Inspection Photos Taken
M.Gagnidze______ F TRU2068MN08 yes
Contractor’s Name Sample Number
LVI Environmental
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner's Name
TRC Environmental Corp The Lower Manhattan Development Corp.
Address City Address City
1340 Broadway New York One Liberty Plaza New York
State Zip Phone State Zip Phone
NY 10018 NY 10006 (212) 962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr. Proj. Mgr/TRC Environmental 1:40 pm to 2:50 pm
I arrived at the premise at 1:40 pm, proceeded to the decon, signed the log book, don the appropriate level of
personal protective equipment to enter the regulated area on 3'^floor One worker was present for the decon
maintenance, organizing the clean room
S"* Floor - 33 workers were present in the floor. Eagle scaffolding workers were erecting the scaffolds above
the escalator, located between 3'" and 2"" floors. Carpenters were setting up platforms across the shafts.
Workers on scissor lifts were removing insulation, demolishing the air ducts at various locations of the work
area, spraying with amended water. Others cutting metal into the pieces, using power tool with HEPA vacuum
attached, spraying the area with amended water, wrapping beams with poly, preparing boxes. 15 Gaylord
boxes were on the floor sealed, sprayed and ready for load out. Inspection was done on micro trap machines
and tents.
I used B stairwell to proceed to the 2"“ floor,
2"“ Floor - 48 workers were found inside the work place. Workers on scissor lift were taking down partition at
the east side of the area, eagle scaffolding workers were erecting the scaffold above the escalator , located
between 2"“ and 3'“ floors, demolishing the brick wall at the east side shaft, using hammer, taking down metal
frames from the ceiling, spraying with amended water around the area, picking up debris and placing into the
boxes; two workers on scissor lift at the east side of the work area were cutting metal from the ceiling; cutting
air ducts and pipes inside the mezzanine, located between 2"'' and V floors; cutting pipes and metal fixtures I
from the ceiling. Others cutting metal into the pieces, using power tool with HEPA vacuum attached, spraying
the area with amended water, wrapping beams with poly, preparing boxes, 20 Gaylord boxes were on the floor
sealed, sprayed and ready for load out, 35 micro trap machines were powered on and 5 on stand by. Inspection
was done on micro trap machines and tents,
I used B stairwell to proceed to the V floor,
1’* Floor - 42 workers on the floor were demolishing the wall, spraying with amended water, placing debris into
the boxes; demolishing the drop ceiling, cutting metal and placing into the boxes, preparing, wrapping and
loading out boxes through the waste decon, A large amount of debris and poly wrapped beams exists on the
floor. 20 Gaylord boxes were on the floor ready to be taken out. Inspection was done on micro trap machines
and tents.
I used B stairwell to go back to the 3'''floor.
After following the decontamination procedure I signed the log book and used south hoist to return to the
ground floor.
Inspection was done on ATC trailer.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor’s^ial
Borough l=Manhallan 2=Bronx 3=Brooklyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code I = Violation Issued 2=No Violation Issued 3=No access 4=Hroject not started (no NOV)
5=Public Owned Property