NYC 9/11 Public Portal Document
Shift Overlap Meeting Minutes
DATE: November 17, 2001
SHIFT GOING OFF: 3:00 pm-11:00 pm
SHIFT GOING ON: 11:00 pm-7:00 am
Meeting Attendants: (See attached sign in sheet)
Companies/Organizations Represented:
1. Amec
2. ATC
3. Bovis
4. DDC
5. Liberty Mutual
6. Tulley
Sector Reports:
AMEC SECTOR
Work in Progress:
• Removing steel and debris from WTC 1;
• Removal of demolition debris from WTC 6;
• Removal of debris slide from WTCl on SW corner of WTC6;
Safety Observations:
• Angel Airial not tieing off while on top of water truck;
• Angel Airial using 6’ lanyards while on truck, should be using shorter lanyards;
• Man baskets need overhead protection;
• Crane on ramp to WTC 6 will be replaced by a wider crane, thereby requiring fall
protection to be removed. New crane will be wide enough to preclude personnel
access to the crane pad thereby eliminating fall hazard;
BOVIS SECTOR
Work in Progress:
• Debris removal at WTC 2;
Safety Observations:
• Bovis concerned that Liberty Mutual tickets indicate safety violations in the
Bovis zone that may not be the responsibility of Bovis. Tully is responsible for
the correct installation of the personal fall arrest system currently installed along
CITY_21MC100_0 06344153
NYC-WTC_000234792