Asbestos Inspection Report
Pre.mise'HrdT Inspection Date:
130 Liberty Street 09/05/08
Floor Zip Borough Block Lot Squad # Badge #
Various 10006 1 54 1 1 A062
Inspector Building Type Basis of Inspection Photos Taken
M.Gagnidze A TRU0086MN08 no
Contractor's Name Sample Number
LVI Environmental
Address City Sample Number
State Zip Phone Sample Number
Laboratory Name Owner's Name
TRC Environmental Corp The Lower Manhattan Development Corp.
Address City Address City
1340 Broadway New York One Liberty Plaza New York
state Zip Phone State Zip Phone
NY 10016 NY 1 6 (212)962-2300
Contact Person Time of Inspection from:
Arnel Javal, Sr. Proj, MgrfTRC Environmental 5:10 pm to 6:15 pm
I arrived at the premise at 5:10 pm.
LVI informed that scheduled activities include fine cleaning on the 15“ and 14“ floors,
and demolition, boxing debris, cut raceway on 13“ floor.
I entered the decon area, suit up, don respirator and entered containment on 15"’ floor.
Two workers were present cleaning in decontamination enclosure system.
15“ Floor - 25 workers were observed on site. Three electricians were found working in
electrical room, wrapping electrical wires with poly. Eight workers were on platform cleaning
beams and columns in the shaft area, 4 workers were in the process of putting rails to construct
the platform between the electrical room and shaft area. Three workers on the west side of
the area were cleaning the floor. Five Gaylord boxes were ready for load out. Inspection was done
on micro trap machines and micro trap tents - air monitoring pumps were on.
20 Micro trap machines were powered on and 5 were on stand by.
I used B stairwell to proceed to the M*" Floor.
14“ Floor - Twenty five workers were present on the floor, cleaning beams and ceiling
on the west side of working area. Eight workers on 4 scaffolds were observed cleaning and
scraping beams around the shaft area. Additional workers were cleaning the floors around
the work areas and vacuuming up the water from the ceiling cleaning. One worker was
observed on ladder working with a hammer. Worker was fine spraying amended water
in the work area. 2 other workers were found in the process of preparing the boxes.
7 Gaylord boxes were ready for load out.
20 micro trap machines were powered on and 5 were on stand by.
Inspection was done on micro trap tents.
I used B stairwell to proceed to the 15“ Floor.
13“ Floor-Was no activity or personnel observed on the floor.
I used B stairwell to go back to the 14“ Floor, proceeded to the decon,
Showered out and signed the log book.
I returned to the ground floor using the north hoist.
Inspection was done on ATC trailer.
NOV# Infraction Infraction Infraction Infraction
NOV# Infraction Infraction Infraction Result Code
2
NOV# Infraction Infraction Infraction Supervisor’s Initial
Borough l=Manhattan 2=Bronx 3=Brooklyn 4=Queens 5=Richmond
Building Type A >6 stories B <6 stories C single family D school E hospital F public owned
Result Code 1 = Violation Issued 2=No Violation Issued 3=No access 4-Projecl not started (no NOV)
5=Public Owned Property