AMBASSADOR CONSTRUCTION CO, INC.
January 18, 1999
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York. NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center
1, 7 & 23rd Floors
Change Order #054
Ainb.JobL#S57:S178
Dear Mr. Weems:
We are pleased to submit herewith our change order #054 for work performed on a
time and material bast* requested by the OEM and DCAS for the sum of TWO
THOUSAND SIX HUNDRED SEVENTY DOLLARS ($2,670.00):
SCOPE QE WORK
As per R.B Samuels work order #26341 the electricians took delivery of various
computer equipment and moved it to the P.l.U. room on the 23rd Floor.
This work was performed on regular and overtime hours as per the following:
Straight time 19 hours; x 95.80 $1,820.00
Overtime 3.6 hours x 138.35 4.84.00
Subtotal $2,304.00
General Conditions 184.00
Overhead & Fee 149.00
Insurance 33.00
Total $2,670.00
We trust the above meets with your approval and we look forward to th e continued
pleasure of serving you.
Continued...