NYC Office Of Emergency Management Work completion required for Motorola to start Installation
23 Floor:
• Electrical Riser to Equipment room 11/10/98/ • Air-conditioning ll/10/98( • Raised Floor 11/13/98 ; • Painting 11/13/98 \ • Room construction 11/13/98 5
Roof Shelter and Antenna Mounting:
• Approve mounting details ^6r31 antenn^ 9/1/98 • Complete I - Beam mountinglorant^nas 10/15/98 • Grounding for roof area antennas/Shelter 10/15/98 • Electrical riser to shelter 10/15/98'3 • Complete radio room construction 10/15/98 1 • Complete Air conditioning 10/30/98 J • Complete Painting 11/1/98^ • Complete Riser for the radio cables to 23 fl 11/1/98
Robert B. Hudson 8/1/98
NYC-WTC_000173793
OCR can misread numbers and units. Confirm readings against the page image before using them.
Related records
Browse subjects →Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
Same-box records
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.964
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173555
Architectural firm observation regarding ceiling conditions on the 23rd floor at OEM offices following site walkthrough.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.923
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166699
Minutes from the 18th consultant meeting at 7 World Trade Center dated November 24, 1998.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.922
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173575
Request for Information log documenting responses to queries about wall offsets and electrical outlet locations at the Mayor's Office of Emergency Management.
1 shared non-person entities · Same agency, volume and box · similarity 0.906
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173794
Timeline tracking project milestones and vendor activities for the Mayor's Office of Emergency Management installation.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.873
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166743
Cover sheet for the Request for Information log documenting 37 received RFI items for the 7 World Trade Center project as of September 16, 1998.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.869
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000167941
Project schedule chart for the Mayor's Office of Emergency Management spanning September through December 1998.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.865
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173854
Meeting minutes from Ambassador Construction regarding project status for the Mayor's Office of Emergency Management at 7 World Trade Center.
1 shared non-person entities · Same agency, volume and box · similarity 0.861
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000167734
Memo summarizing outstanding OEM equipment product data and catalog cuts for the Mayor's Office of Emergency Management project at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.857
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173652
Log of incoming and outgoing faxes between Ambassador Construction and the Office of Emergency Management regarding project communications.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.854
machine-extracted · confidence unavailable · Check page ↗Filed elsewhere
NYC-WTC_000140959
Form authorizing the City of New York to proceed with obligations related to FEMA emergency management programs for WTC cleanup.
1 shared non-person entities · similarity 0.856
machine-extracted · confidence unavailable · Check page ↗More like this page
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Similarity score 0.998 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173575
Request for Information log documenting responses to queries about wall offsets and electrical outlet locations at the Mayor's Office of Emergency Management.
Similarity score 0.993 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166743
Cover sheet for the Request for Information log documenting 37 received RFI items for the 7 World Trade Center project as of September 16, 1998.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166699
Minutes from the 18th consultant meeting at 7 World Trade Center dated November 24, 1998.
Similarity score 0.988 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173555
Architectural firm observation regarding ceiling conditions on the 23rd floor at OEM offices following site walkthrough.
Similarity score 0.987 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000166730
Log entries recording received faxes and requests for information related to the 7 World Trade Center project in 1995.
Similarity score 0.985 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Others also read
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Similar indexed content
Similar indexed content
NYC-WTC_000173555
Architectural firm observation regarding ceiling conditions on the 23rd floor at OEM offices following site walkthrough.
Similar indexed content
NYC-WTC_000166699
Minutes from the 18th consultant meeting at 7 World Trade Center dated November 24, 1998.
Similar indexed content
NYC-WTC_000173575
Request for Information log documenting responses to queries about wall offsets and electrical outlet locations at the Mayor's Office of Emergency Management.
Similar indexed content