NYC 9/11 Public Portal Document
Mayors Office of Emergency Management Project
September October November December January
ID Task Name Duration Start 8/30 I 9/6 I 9/13 I 9/20 | 9/27 | 10/4 | 10/11 | 10/18 | 10/25 11/1 Lil'S [11/15 J 11/22 j 11/29j 12/6 L12/13 L 12/20 j 12/27 J 1/3 J 1/10 | 1/17
1 Purchase Order Approved Id 9/1/98 Hem
2 Order Material Id 9/4/98 ^-Engineering
3 Material Delivery 60d 9/7/98 |-|Motorola
4 Develop site Drawings 30d 9/7/98 |ram Manager
5 cost Staging 29d 11/2/98
6 CCSI staging Build 25d 11/2/98 [-Motorola
7 CCSI Customer Demo 2d 12/7/98 ^J-|OEM,Motorola
8 Ship to #7 WTC/Sites AS 2d 12/9/98 ^Motorola
9 #7 me 23 Floor- WC 65d 10/2/98
10 Site Hreparaton 50d 10/2/98 imuels,Motorola,Swanki
11 Install CEB Room lOd 12/11/98 Samuels, =SO, Motorola
12 Install 4 Console Furnitur 8d 11/27/98 muels,Motorola,FSO
13 Install 3 Console Electro lOd 12/11/98 FSO,Mot( rola
14 Install Premisys in LAN 5d 12/11/98 ^Motorola
15 Install RCH3000 units lOd 12/18/98 F 3O,Motorola
16 #7 WTC Root Radio Room// 49d 10/19/98
17 Site Prep at #7 WTC Rot 30d 10/19/98 Swanke,Samu< Is
18 Install Electrical on roof lOd 10/19/98 Samuels,Motorola
19 Install Antenna Mounts a lOd 10/19/98 imuels,Motorola
20 Install Ant and lines at #7 5d 11/2/98 Samuels,Motorola
21 Install radios on Roof lOd 12/11/98 FSO,Mot( rola
22 Install riser cables 5d 10/19/98 n Samuels,Motorola
23 System Optimization lOd 1/1/99 ,FSO,Mol
24 Training 3d 1/15/99 Mo
25 Acceptance Testing 5d 1/15/99
26 Final Sign Off Id 1/22/99
Task Milestone Rolled Up Task
Project: NYC Mayor's OEM Project
Date: 8/3/98 Progress Summary Rolled Up Milestone O
Prepared by Robert Hudson Page 1
NYC-WTC_000173794