Minutes of Consultant Meeting #17, 7 WTC, Nov 1998

Machine-extracted title · confidence 100%

Meeting minutes from Ambassador Construction regarding project status for the Mayor's Office of Emergency Management at 7 World Trade Center.

NYC-WTC_000173854–000173856

Folder label: “MINUTES OF CONSULTANT'S MEETING #17

Page image
Scanned page image, NYC-WTC_000173854
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

AMBASSADOR CONSTRUCTION CO, INC.

MINUTES OF CONSULTANT’S MEETING #17

PROJECT: Mayor’s Office of Emergency Management 7 World Trade Center -1, 7 & 23rd Floors Amb. Job#S57-5175

DATE: November 17, 1998

PRESENT: Martin Schneider Ambassador Jack Klein Ambassador M. Mathew DCAS Glenn Pymento DCAS Marty Meehan SPI Jerry Caramico Motorola Tom Gorman Motorola Paul Radtnan Motorola

1. PROJECT STATUS 1st Floor: - Burn out steel on 11/14 - Installation of piping for fuel oil tank is on hold. Architect and engineer wi I look at alternate route. Original route does not work due to steel interference. - Steel installation to start this week~=— i - Samuel to move bells and camera 11/18. hh Floor: - Emergency generators were delivered 11/6 - Waterproofing to start the week of 11/16 — - Water storage tank work is to start the week of 11/16 - ATS switches and transfer switch will ship tomorrow - Waterproofing to start this week. - Water storage tank installation to begin this week-- • if/ - ATS switches to be delivered 11/18 - Piping to emergency (electrical) is starting this week 23rd Floor.- Raised flooring started 11/5 about 60% complete - Acme walls will be delivered 11/20-11/21 - Waterproofing in machine room is complete - Ambassador advised that hurricane damper sleeves are being installed. - Hurricane dampers to be delivered Monday 11/23 Roof: - Steel work was complete 11/16 - Concrete to be poured 11/17 - Metal panel wall will be delivered next week - Ambassador advised the antenna supports are in fabrication - All electrical risers have been completed to the roof. Penetrations thru roof to be completed after room is tight.

Continued. . .

317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762

NYC-WTC_000173854

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000173854Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Consultant meeting minutes #18 for OEM, Nov 1998 · Box 7DCAS

NYC-WTC_000173557

Minutes from Ambassador Construction Co. regarding project status and fuel oil piping routes at the Mayor's Office of Emergency Management.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.966

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →