AMBASSADOR CONSTRUCTION CO, INC.
Mr. Walter Weems
September 11,1998
Page Two...
Hurricane Wall
This is in addition to the letter of June 11,1998 (copy attached)
1. Additional labor and framing for new duct openings. $4,000.00 lZ
2. Patch twenty two (22) existing columns; wall runs in front of
column. $2,800.00
3. Add 24lf of hurricane partition thru columns. $11,000.00
Auu layer sheeiiuck of 2001f to Hurricane wall as shown on
Sections 6 and 12 on D-13. $4,300.00
5. Deletion of top of wall. <$15,000.00>
6. Additional work to furnish material and labor for the steel
reinforcement for Blast proof access doors (19) and Blast
orccf doors (7). 201 pieces of steel >2 plate 8"x8" and wood
blocking as per FSK-11. $13,750.00 vX'
7. Remove existing column fronts (19), for new location of
Hurricane wall. $1,750.00
8. Leak detection system (additional to budget).
9. Electrical work on Hurricane dampers in ductwork (22) to
be connected to the new ASCO #917 from panel ELP-23B1,
Furnish and install override switch in watch commander’s
station desk with indicator light to be operated manually.
Dampers not tied into fire alarm system. $20,700.00lZ
10. Additional steel 3"x3" x 5/16" steel angle welded to
spandrel as shown on DI 3. $14,800.00
11. Additional work on Hurricane damper duct to duct
refabricating and install new duct four (4) locations. $8,212.00
12. Additional work on Hurricane dampers and fire smoke dampers
(15) locations of refabricating and installing new duct. $30,794.00 '
13. Five (5) locations of Hurricane dampers with flexible connections,
additional ductwork as required. $7,305.00
Forward.../