AMBASSADOR CONSTRUCTION CO, INC.
♦
Mr. Walter Weems
September 11, 1998
Page Two...
Hurtlcane_Wall
This is in addition to the letter of June 11,1998 (copy attached)
1. Additional labor and framing for new duct openings. $4,000.00
2. Patch twenty two (22) existing columns; wall runs in front of
column. $2,800.00
7 3. Add 24lf of hurricane partition thru columns. $11^.00
'^iCOO
4. Add layer sheetrock of 200lf to Hurricane wall as shown on
Sections 6 and 12 on D-13.
5. Deletion of top of wall.
6 Additions! 'work to fi irnish mafpria! ond labor for the steel
reinforcement for Blast proof access doors (19) and Blast
proof doors (7). 201 pieces of steel 14 plate 8"x8" and wood
blocking as per FSK-11. $13,750.00
7. Remove existing column fronts (19), for new location of
Hurricane wall. $1,750.00 /
? 8. Leak detection, systep (additional to budgeit). $11,975.00
9. Electrical work on Hurncane campers in ductwork (22) to
be connected to the new ASCO #917 from panel ELP-23B1,
Furnish and install override switch in watch commander’s
station desk with indicator light to be operated manually.
Dampers not tied into fire alarm system. $20,700.00
10. Additional steel 3"x3" x 5/16" steel angle welded to
spandrel as shown on DI 3. $14,800.00
11. Additional work on Hurricane damper duct to duct
refabricating and install new duct four (4) locations. $8,212.00
10^44^
12. Additional work on Hurricane dampers and fire smoke dampers
(15) locations of refabricating and installing new duct. $30,794.00
13. Five (5) locations of Hurricane dampers with flexible connections,
additional ductwork as required. $7,305.00 X
Fonward.../