Same-box records
Cost estimate correspondence, 7 WTC, June 1998 · Box 7DCASNYC-WTC_000173153
DCAS letter to contractor regarding cost estimates for Mayor's Office of Emergency Management work at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.979
DCAS letter re: cost estimates, Mayor's OEM project, July 1, · Box 7DCASNYC-WTC_000173155
Letter from DCAS dated July 1, 1998, detailing original and revised cost estimates for the Mayor's Office renovation.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.968
Correspondence regarding cost estimates for Mayor's OEM project, June 1998 · Box 7DCASNYC-WTC_000173149
A letter from the Division of Real Estate Service referencing original and revised cost estimates for renovation work at the Mayor's Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.967
DCAS letter on construction cost estimates, July 1998 · Box 7DCASNYC-WTC_000167308
Letter from DCAS reviewing and summarizing documentation for construction cost estimates for the Mayor's Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.967
Construction cost estimate approval, 7 World Trade Center, July 1998 · Box 7DCASNYC-WTC_000173421
Memo summarizing reviewed documentation and approving revised trade cost estimates for the Mayor's Office of Emergency Management project.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.966
Minutes of Consultant's Meeting #1: Shop drawing status, July 1998 · Box 7DCASNYC-WTC_000173789
Record of a meeting reviewing the status of HVAC and other shop drawings for the Mayor's Office of Emergency Management project.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.965
Change order review correspondence, 7 World Trade Center, Aug 1999 · Box 7DCASNYC-WTC_000168379
Letter from Citywide Administrative Services reviewing and negotiating costs for multiple change orders at the Mayor's Office of Emergency Management.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.954
Change order approvals #93, #97, #99 & #100, 7 WTC, · Box 7DCASNYC-WTC_000168365
Department memo approving costs for shade motor installation and circuit work at the Mayor's Office of Emergency Management facility.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.954
Approval of Change Orders 93, 97, 99 & 100 for · Box 7DCASNYC-WTC_000171334
Letter from DCAS approving costs for four change orders related to electrical and audiovisual work at the Mayor's Office of Emergency Management.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.953
DCAS response to clarifications, 7 WTC, June 2, 1998 · Box 7DCASNYC-WTC_000172121
DCAS letter responding to contractor's clarifications regarding the Mayor's Office of Emergency Management project at 7 WTC.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.953
DCAS letter on negotiated change orders #73-95, Nov 1999 · Box 7DCASNYC-WTC_000171646
Letter from DCAS confirming review and cost negotiation for ten change orders submitted by a contractor for the Mayor's Office of Emergency Management.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.951
DCAS approval memo, change order #108, Jan 2000 · Box 7DCASNYC-WTC_000171568
Department of Citywide Administrative Services letter dated January 3, 2000 approving $4,258.00 for change order #108 regarding video cable connections.
2 shared non-person entities · Same agency, volume and box · similarity 0.947