NYC 9/11 Public Portal Document
DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES
DIVISION OF REAL ESTATE SERVICES
MUNICIPAL BUILDING. - Room 2002 S
NEW YORK, N.Y, 10007
(212)669-8086 FAX (212) 669-3640
WILLIAM J DIAMOND LORI FIERSTEIN
Commissioner Deputy Commissioner
October 27. 1999
Ms. Catherine T. Giliberti
Silverstein Properties, Inc
7 World Trade Center
New York, New York 10048
Re; Change Order # 93, 97, 99 & 100
Mayor's Office of Emergency Management
7 World Trade Center
New York, New York
Dear Ms Giliberti:
We write with reference to CO # 93, 97,99 & 100 submitted by Ambassador Construction Company
on 8/6, 9/24,10/4 & 10/27/99 respectively.
The change orders have been reviewed and the costs have been approved as shown below;
CO# Description of Work Amount Approved
93 Wire Six (6) shade motors and 2 switch
controllers with new circuit form panel
in PIU room. $ 4,892.00
97 Additional cost for fire rating fuel oil line
with sheet rock instead of vermiculate $ 4,560.00
99 Additional electrical work at Jack’s
office as per request from
Raymond M. Lynch $ 2,033.00
100 Engineering fee for Shen Milsom &
Wilke, Inc regarding DOT cameras $20,625.00
Total $32,110.00
In view of the foregoing an amount $32,110.00 is hereby approved, subject to audit, for the above change
orders.