← Document results/7DCAS/Change Order #98 & 103®Mayor's Office of Emergency Management®7 World Trade Center®breakdown of project's budget
Document / 2 pages

Memo approving change orders #98 and #103, April 1999

Machine-extracted title · confidence 95%

City memo approving costs for electrical lighting changes and press feed camera installation at the Mayor's Office of Emergency Management.

NYC-WTC_000171322–000171323

Folder label: “Change Order #98 & 103®Mayor's Office of Emergency Management®7 World Trade Center®breakdown of project's budget

Page image
Scanned page image, NYC-WTC_000171322
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES DIVISION OF REAL ESTATE SERVICES MUNICIPAL BUILDING, - Room 2002 .S NEW YORK, N.Y. 10007 (212) 669-8086 FAX (212) 669-3640

WILLIAM J. DIAMOND LORI FIERSTEIN Commissioner Deputy Commissioner

November 15, 1999

Ms. Catherine T. Giliberti Silverstein Properties, Inc 7 World Trade Center New York, New York 10048

Re: Change Order # 98 & 103 Mayor’s Office of Emergency Management 7 World Trade Center New York, New York

Dear Ms Giliberti:

We write with reference to CO#93 & 103 submitted by Ambassador Construction Company on 9/30 & 11/3/99 respectively.

The change orders have been reviewed and the costs have been approved as shown below:

CO# Description of Work Amount Approved

98 Various electrical lighting changes in Press Room and Mayor’s conference room. $ 8,800.00

103 Press feed. Press Room camera and three (3) wireless microphones $ 73,987.00

Total $ 82,787.00

In view of the foregoing an amount $82,787.00 is hereby approved, subject to audit, for the above change orders.

The following is a breakdown of the project’s budget.

Construction Cost Budget $14,287,986.00 Construction Cost Budget (revised) $14,287,986.00 Less Landlord’s Construction $ 1.668,858.00 Maximum amount Chargeable to City $12,619,128.00 Construction cost approved on 6/2/98 $12,864,619.00 Amount approved by CO on 7/8/98 $ 117,684.00

NYC-WTC_000171322

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171322Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change order approvals #98 & #103, 7 WTC, 1999 · Box 7DCAS

NYC-WTC_000168363

Department memo approving costs for electrical lighting changes and press feed camera work at the Mayor's Office of Emergency Management.

4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.996

machine-extracted · confidence unavailable · Check page ↗
Approval letter for Change Order #104, Nov 1999 · Box 7DCAS

NYC-WTC_000171623

Letter from DCAS approving a negotiated cost of $50,000 for conduit and fiber optic installation at the Mayor's Office of Emergency Management.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.988

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171502 · Box 7DCAS

Department approval of change orders totaling $19,732 for electric space heaters and valve replacement in the generator room at 7 World Trade Center.

Similar indexed content

Compare copies and versions →