municipal building. - Room 200,
NEW YORK, N.Y. 10007
(212) 669-8086 FAX (212) 669-3640
WILLIAM J. DIAMOND
Commissioner LORI nuRs-rtiN
Deputy Commissions
February 9, 2000
Ms. Catherine T. Giliberti
Silverstein Properties, Inc
7 World Trade Center
New York, New York 10048
Re: Change Order # 96,109 & 110
Mayor’s Office of Emergency Management
7 World Trade Center
New York, NY
Dear Ms Giliberti:
We write with reference to CO # 96,109 & 110 submitted by Ambassador Construction Company
on 11/3/99, 1/7/00 & 1/25/00. The proposals are in the amounts of $10,255.00 for heat tracing of 6” hot
water piping on 7'*’ floor, $4,482.00 for various electrical work on 23"* floor and $2,461.00 for providing a
sprinkler head on 1 floor tank room respectively.
The change orders have been reviewed and the costs have been found fair and reasonable.
Therefore, in view of the foregoing an amount of $17,198.00 is hereby approved, subject to audit, for the
above change orders.
The following is a breakdown of the project’s budget:
Construction Cost Budget (revised) $14,287,986.00
Less Landlord’s Construction $ 1,668,858.00
Ma.ximum amount Chargeable to City $12,619,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/21/98 $ 102,705.00
Amount approved by CO on 10/22/99 $ 28,442.00
NYC-WTC_000171297