DCAS memo regarding OEM change orders #114 and #115, Dec

Machine-extracted title · confidence 50%

Department of Citywide Administrative Services memo approving two change orders totaling $40,485 for lock-out switches and an Inergen system at the Mayor's Office of Emergency…

NYC-WTC_000171480–000171481

Folder label: “Change Order # 114 & 115 Mayor's Office of Emergency Management 7 World Trade Center New York, NY

Page image
Scanned page image, NYC-WTC_000171480
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES DIVISION OF REAL ESTATE SERVICES

MUNICIPAL BUILDING, 20'" Floor, Room 2053 S NEW YORK, N.Y. 10007 (212) 669-3645 Fax (212) 669-2666 E-Mail:iricrstc(a'.dcas.nyc.gov

WILLIAM J. DIAMOND LORI FIERSTEI.N CoiHfuissio/ier Deputy Coinmissio/ier

December 18, 2000

Ms. Catherine T. Giliberti Silverstein Properties, Inc 7 World Trade Center New York, New York 10048

Re: Change Order# 114 & 115 Mayor’s Office of Emergency Management 7 World Trade Center New York, NY

Dear Ms. Giliberti;

We write with reference to CO # 114 & 115 submitted by Ambassador Construction Company on 11/16/00 and 12/6/00 in the amounts $1,221.00 & $39,264.00, for providing new lock-out switch in the tank room and F&I connected reserve Intergen system respectively.

The change orders have been reviewed and the costs have been found fair and reasonable. Therefore, in view of the foregoing, an amount of $40,485.00 is hereby approved, subject to audit, for the above change orders.

The following is a breakdown of the project’s budget:

Construction Cost Budget (revised) $14,287,986.00 Less Landlord’s Construction Maximum amount Chargeable to City $12,619,128.00 Construction cost approved on 6/2/98 $12,864,619.00 Amount approved by CO on 7/8/98 S 117,684.00 Amount approved by CO on 8/11/98 S 7,000.00 Amount approved by CO on 9/21/98 S 102,705.00 Amount approved by CO on 10/22/99 S 28,442.00

The Official New York City Web Site nyc.gov

NYC-WTC_000171480

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171480Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

DCAS memo regarding OEM change order #113, Nov 2000 · Box 7DCAS

NYC-WTC_000171493

Department of Citywide Administrative Services memo approving a $3,253.00 change order for a self-closing hatch in the tank room at the Mayor's Office of Emergency Management.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.987

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171502 · Box 7DCAS

Department approval of change orders totaling $19,732 for electric space heaters and valve replacement in the generator room at 7 World Trade Center.

Similar indexed content

NYC-WTC_000171417 · Box 7DCAS

Letter approving a $762 change order for the installation of a disconnect switch for a hatch door release at 7 World Trade Center.

Similar indexed content

Compare copies and versions →