In view of the above, an amount of $102,705.00 is hereby approved, subject to audit, for the
above referenced change orders.
The following is a breakdown of the project’s budget:
Construction Cost Budget $14,287,986.00
Construction Cost (Budget Revised) $13,727,986.00
Less landlord’s Contribution $ 1,668,858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by this CO $ 102,705.00
Total construction cost approved $13,092,008.00
Less landlord’s contribution $ 1,668,858.00
Amount chargeable to the City $11,423,150.00
Balance remaining in Budget $ 635,978.00
If you have any questions, please call Gleim Pymento at 212-669-8094. Thank you for your
cooperation.
'Richard J. Ramos
Executive Director of Space Design/DRES
cc: G. Pymento, DRES
V. Castagnola, DRES
J. Domingvez, DRES i
M. Mathew, DRES —
J. Menasce, DRES
W. Weems, Silverstein Properties, Inc.
c:gilberti/98F2654/mathew/ip
NYC-WTC_000167187
OCR can misread numbers and units. Confirm readings against the page image before using them.