In view of the above, an amount of $42,887.00 is hereby approved, subject to audit, for the referenced
change orders.
The following is a breakdown of the project’s budget;
Construction cost Budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord’s Contribution $ 1.668,858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/14/98 $ 102 ,705.00
Amount approved by CO on 9/21/98 $ 28,442.00
Amount approved by CO on 10/22/98 $ 26,483.00
Amount approved by this CO $ 42,887.00
Total Construction cost approved $13,189,820.00
Less Landlord’s contribution $ 1,668.858.00
Amount chargeable to the City $11,520,962.00
Balance remaining in Budget $ 538,166.00
If you have any question, please call Glenn Pymento at (212) 669-8094. Thank you for
your cooperation.
Sil il:
Richard J: Ramos
Executive Director of Design/DRES
c: G. Pymento, DRES^^
V. Castagnola, DRES
L Doiaiogv,^ DRBS
M. Mathew, DRES
J. Menasce, DRES
W. Weems, Silverstein Properties, Inc.
c;giliberli3/mm/ip
NYC-WTC_000167179
OCR can misread numbers and units. Confirm readings against the page image before using them.