-2-
In view of the above, an amount of $28,442.00 is hereby approved, subject to audit, for the referenced
change orders.
The following is a breakdown of the project’s budget:
Construction cost Budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less landlord ‘s Contribution $ 1,668,858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/14/98 $ 102,705.00
Amount approved by this CO $ 28,442.00
Total Construction cost approved $13,120,450.00
Less landlord ‘s contribution $ 1,668,858.00
Amount chargeable to the City $11,451,592.00
Balance remaining in Budget $ 607,536.00
If you have any question, please call Glenn Pymento at 212-669-8094. Thank you for your cooperation.
Siifc.
'ichard J: Ramos
Execution Director of Design/DRES
c: G. Pymento, DRES
V. Castagonla, DRES
J. Domingvez, DRES
M. Mathew, DRES
J. Menasce, DRES
W. Weems, Silverstein Properties, Inc.
c:giliberti/mm7kc
NYC-WTC_000167185