NYC 9/11 Public Portal Document
DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES
IS MUNICIPAL BUILDING, 17tli Floor
NEW YORK, N.Y. 10007
(212) 669-7111 Fax (212) 669-8992
WILLIAM J. DIAMOND LORI FIERSTEIN
Commissioner Deputy Commissioner
January 4, 1999
Ms. Catherine T. Giliberti
Silverstein properties, Inc.
7 world Center, New York ,NY
Re: Change order it 47
Mayor’s Office of Emergency Management
7 World Trade Center, New York, NY
Dear Ms. Giliberti:
We write reference to the change order # 47 submitted by Ambassador Construction Co. on 12/31/98
in the amount of $3,941.00 for the supply of three (3).stainless steel flexes for the generators in lieu of
standard flexes provided originally.
The Change order has been reviewed and the cost has been found reasonable. Therefore, an amount
of $ 3,941.00 is hereby approved, subject to audit, for the referenced change order.
The following is a breakdown of the project’s budget:
Construction cost budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO 9/14/98 $ 102,705.00
Amount approved by CO 9/21/98 $ 28,442.00
Amount approved by CO on 10/22/98 $ 26,483.00
Amount approved by CO on 10/30/98 $ 42,887.00
Amount approved by CO on 12/1/98 $ 125,453.00
NYC-WTC_000171879