DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICE
DIVISION OF REAL ESTATE SERVICE
w MUNICIPAL BUILDING, - Room 2053S
NEW YORK, N.Y. 10007
(212)669-2030 Fax (212)669-3640
WILLIAM J. DIAMOND LORI FIERSTEIN
Com/njssioner Vepufy Commjssioner
March 25, 1999
Ms. Catherine T. Giliberti
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
Re: Change Order #75
Mayor’s Office of Emergency Management
7 World Trade Center
New York, New York
Dear Ms. Giliberti:
We write with reference to CO #75 submitted by Ambassador Construction CO on 3/17/99 in the amount
of $4,874.00 for the supply and installation of UPS system.
The change order has been reviewed and the cost has been found to be fair & reasonable.
Therefore, an amount of $4,874.00 is hereby approved, subject to audit, for die above change order.
The following is a breakdown of the project’s budget:
Construction cost budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord’s Construction $ 1.668.858.00
Maximum amount Chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $117,684.00
Amount approved by CO on 8/11/98 $7,000.00
Amount approved by CO on 9/14/98 $102,705.00
Amount approved by CO on 9/21/98 $28,442.00
Amount approved by CO on 10/22/98 $26,483.00
Amount approved by CO on 10/30/98 $42,887.00
NYC-WTC_000171777