July 1, 1998
Ms. Catherine T. Gilbert!
Silverstein Properties, Inc.
120 Broadway
New York, NY 10271
Re: Mayor’s Office of Emergency Management
7 World Trade Center
1”, 7*, & 23"* Floors
NY, NY
Project # 96-1346
Dear Ms. Gilbert!
We write with reference to the following correspondency with respect to the cost
estimate.
1) Original cost estimate dated May 27, 1998 in the amount of $11,423,238.00.
2) Revised trade cost dated June 10, 1998 including work associated with addendum 1, in
the amount of $11,645,746.00.
3) Cost Estimate dated June 11, 1998 for additional work related to A.V. equipment in the
amount of $34,475.00.
4) Cost of using 9f existing fuel lines in the amount of $302,410.00 dated June 16, 1998.
5) Tapping cost in the amount of $219,800.00 dated June 12,1998.
6) A/E fees proposal in the amount of $91,500.00 dated June 30, 1998 this includes
reimbursable up to a maximum of $14,750.00.
7) Cost estimate incorporating scope reductions/modifications as requested by this office
dated June 26, 1998.