Based on the above the following costs are approved subject to audit.
1. Revised cost bid including addendum 1. $11,645,746.00
2. Additional cost for A & E contractor. $ 34,475.00
—-—------ > 3. Cost to use existing fuel lines. 302,410.00
4? Tapping fees (Electrical)
$
$ 219,800.00
5. A/E fees (Additional reimbursable cost will be approved as a
change order on receipt of documentation up to a maximum
of $14,750.00) $ 76,750.00
6. Cost of generators approved April 17, 1998 $ 717,890.00
7. Scope reduction as per your letter date June 26, 1998 $ 503,388.00
8. Revised “Hurricane Wall” inclusive of bullet proofing as per your4S^x"
letter dated June 26, 1998. $ 356.186.00
\
Total
Construction of the project has to conform fully to the approved drawings afi specifications. No
change orders will be pennitted unless there is a written scope change approved by this office.
The approval of the estimate is based on the aggnmpdnn that^be contractor visited the space
and satisfied himself to the existing conditions and to the work called for in me drawings and
specification. Therefore, the only change order will be for additional work raquested in writting
by this office. 1
The following is a breakdown of the project’s budget.
Construction Cost Budget $14,287,986.00
Landlord’s Contribution $ 1,668,858.00
Amount chargeable to City
i 69 ‘
Construction cost approved $12,8^0H^^
Less Landlord’s contributions $ 1,668,858.00
Amount payable by City $11,181^.00
Balance remaining in Budget $ P, I i 7? . 00
Thank you for your cooperation. I
c: Jerry Hauer, OEM Joseph Menasce, DRES
Lori Fierstein, DRIES Josep Domingvez, DRES
Jeff Kondrat, DRES Patrick Ronan, OEM
Glenn Pymento, DRES
C:gilberti3moem/gp/ip