The following is a breakdown of the project's budget.
Construction Cost Budget $14,287,986.00
Construction Cost Budget (revised) $14,287,986.00
Less Landlord's Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,619,128.00
Construction cost approved on 6/2/98 $12.,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/21/98 $ 102,705.00
Amount approved by CO on 10/22/99 $ 28,442.00
Amount approved by CO on 10/30/98 $ 42,887.00
Amount approved by CO on 12/01/98 $ 125,453.00
Amount approved by CO on 1/4/99 $ 3,941.00
Amount approved by CO on 1/25/99 $ 78,288.00
Amount approved by CO on 2/10/99 $ 22,721.00
Amount approved by CO on 3/11/99 $ 220,262.00
Amount approved by CO on 3/25/99 $ 4,874.00
Amount approved by CO on 4/8/99 $ 85,000,00
Amount approved for fuel oil line $ 130,000.00
Credit amount approved for previously approved fuel line ($ 85,000.00)
Credit amount approved by CO on 9/9/99 ($ 419.00)
Amount approved by this CO $ 32,110.00
Total construction cost approved $13,834,871.00
Less Landlord contribution $ 1,668,858.00
Amount chargeable to the City $12,166,013.00
Balance remaining Budget $ 453,115.00
If you have any question, please call Glenn Pymento at (212) 669-8094 or myself at (212) 669-8086.
Thank you for your cooperation.
Sinc^aely,
Richard J Ramos
Executive Director of Space Design/DRES
cc: G. Pymento, DRES<; M.Mathew, DRES Igliu
V. Castagnola, DRES J. Menasce, UKES
J. Domingvez DFlES W.Weems,Silverstein Properties, Inc
C:/mydoc/constbud/oem/giliberti2/mni
NYC-WTC_000171335
OCR can misread numbers and units. Confirm readings against the page image before using them.